A part of Chucky Mullins Drive, from South Poole Drive to Fraternity Row, will be closed to traffic from March 29 to April 2 due to a construction project, according to an
The Ole Miss Student Union opened on Monday morning, over ten million dollars over budget and nearly a year late. A bookstore, coffee shop and conference rooms opened for the first time
The construction of a paid parking garage on the Square began last August and after several initial delays, the new completion date is set for September 19, 2019. With the parking lot
Nearly a year after its closure in the summer of 2018, Chucky Mullins Drive has reopened to commuter traffic. The university initially planned for the closed portion of Chucky Mullins Drive to
Music echoed throughout the University of Mississippi campus every Tuesday and Thursday during the fall of 2016. Synchronized claps, shouts and stomps permeated the damp Mississippi air, from the Paris-Yates Chapel to
The Ole Miss Student Union’s almost four-year-long construction and renovation is set to be complete early in the 2019 spring semester. The project costs over $50 million and will include an additional
With roads closed, walkways blocked off and green fences everywhere, it feels like campus is constantly under construction and students are never able to truly enjoy all it has to offer. Luckily,
Both Ole Miss and Oxford have felt growing pains as more students attend the university and more people move to town, placing a higher demand on the city’s many stores, restaurants and
Parking on the Square has increasingly become a problem for students, residents and visitors as entering freshman classes grow annually. To combat this problem, the Downtown Parking Advisory Commission has agreed to